Frames And Gantries
Portal frames, mezzanines, gantries, platforms and racking cut down in an order that keeps what is left standing. Steel is weighed at a licensed yard and credited against the price.
Sequence
Steel comes down in reverse of how it went up, and the risk is that the drawings on site are not what was actually built. Frames get modified, bracing gets removed for access and never replaced, and mezzanines get tied into columns that were never designed to carry them.
So the sequence is written from a survey of the steel as it stands, not from the original drawings, and temporary support goes in before any member that is carrying something is cut. Where a member is holding a load, an engineer signs the temporary works before it is touched, the same as for shoring and support.
Sections leave the site under debris hauling, and the surrounding structure comes down under structural demolition.
How It Runs
The steel as it stands, not as drawn.
Temporary works in and signed off first.
Members released in a planned order.
Licensed yard, tickets handed over.
The Credit
On a steel-heavy job the recovered tonnage can move the price by a meaningful margin, which is exactly why the two quotes in front of you may not be comparable. A price that looks low often assumes the contractor keeps the steel; a price that looks higher may be crediting it back.
Neither is wrong, but you cannot judge them side by side until you know which is which, and it is a fair question to ask before you choose. We weigh at a licensed yard, hand over the weighbridge tickets and show the credit as its own line on the invoice, so the number can be checked rather than trusted.
Non-ferrous and mixed material is separated under disposal and recycling, salvageable items are handled under deconstruction and salvage, and the wider scope sits under industrial demolition.
Related Work
The envelope and frame together.
Learn moreSteel that carries process equipment.
Learn moreTemporary works before a load is cut.
Learn moreThe structure around the steel.
Learn moreMembers recovered rather than scrapped.
Learn moreSegregated and weighed off.
Learn moreStraight Answers
They told me on day one that the gas cap would take six weeks, not the demolition. That was the whole schedule and they were right.
Quoted a full removal rather than a partial fill, and explained why the cheaper option would show up on a survey later.
The asbestos survey came back positive on the floor tile. They stopped, abated it, gave me the paperwork, then carried on.
Lot was swept and the debris weighed out with a recycling breakdown. Neighbours never complained once about dust.
Next Step
Send the address and any drawings or survey you already hold. We will tell you what the scope really is before we price it.
Licensed and insured · Permit and inspection included · Written quotes, itemized