A demolition permit is rarely the thing that delays a job. The notification period, the asbestos survey and the utility disconnections all run on their own clocks, and the longest of them decides when work can actually begin.
Utility Disconnects
This is the part almost everyone underestimates. Closing the electric account, having the meter removed and the service line disconnected commonly takes seven to fourteen business days. Removing a gas meter and capping the supply at the main takes considerably longer, in the region of twenty one to sixty business days, and where the gas source is within about five feet of demolition activity the riser has to come out as well.
Utility providers generally require the property owner to request these, not the contractor, so nothing moves until you make the calls. Start them first, before the permit and before booking anyone. We tell you exactly which calls to make and in what order.
Line locates are arranged under site clearing, and the demolition itself follows under house demolition or commercial demolition.
How It Runs
Owner requests disconnects; start here.
Required before commercial work begins.
Permit filed, notification period runs.
Underground lines marked, then work begins.
Notification
Commercial demolition typically requires an asbestos survey and a notification to the regulator before work begins, and that period runs in calendar days regardless of how ready everyone else is. It cannot be compressed by paying more or by starting quietly, and starting without it is an enforcement matter rather than a paperwork oversight.
The practical consequence is that a programme showing machines on site next week has almost certainly not filed anything. Filing on the day the job is engaged, and booking the survey in the same week, lets those two clocks run alongside the utility disconnections rather than after them, which is what keeps a demolition to weeks instead of months.
Findings are cleared under asbestos removal, and the cost effect of that is set out under demolition cost before emergency demolition becomes the only option.
Related Work
Required before commercial demolition.
Learn moreLine locates called and marked.
Learn moreResidential filing and notice.
Learn moreNotification and coordination.
Learn moreHow permits sit in the price.
Learn moreWhen a structure cannot wait.
Learn moreStraight Answers
They told me on day one that the gas cap would take six weeks, not the demolition. That was the whole schedule and they were right.
Quoted a full removal rather than a partial fill, and explained why the cheaper option would show up on a survey later.
The asbestos survey came back positive on the floor tile. They stopped, abated it, gave me the paperwork, then carried on.
Lot was swept and the debris weighed out with a recycling breakdown. Neighbours never complained once about dust.
Next Step
Send the address and what you intend to remove. We will tell you which filings apply and which calls you need to make first.
Licensed and insured · Permit and inspection included · Written quotes, itemized